How to highlight overdue dates in Google Sheets

Updated October 9, 2026

To highlight overdue dates in Google Sheets, select the date column, open Format → Conditional formatting, choose “Date is before” and “Today”, and pick a red fill. That’s the quick version. Below is the version that skips finished tasks, warns you before things are late, and colors the whole row.

The quick way: past dates turn red

  1. Select the date cells, for example D2:D200.
  2. Open Format → Conditional formatting.
  3. Under “Format cells if”, choose Date is before, then Today.
  4. Pick a red fill or red text, and click Done.

The catch: a task finished last week still shows red, because its date is in the past. For a task list, you almost always want the next version.

Only highlight what isn’t done

This uses a custom formula, so it can check two columns at once. It assumes status is in column B and the due date in column D.

  1. Select the date cells, D2:D200, or the whole table A2:F200 to color entire rows.
  2. In Conditional formatting, choose Custom formula is.
  3. Enter =AND($D2<>"", $D2<TODAY(), $B2<>"Done") and pick a red fill.

Reading it from left to right: the date isn’t empty, it’s before today, and the status isn’t Done. If you track completion with checkboxes in column A, use =AND($D2<>"", $D2<TODAY(), $A2=FALSE).

Why the dollar signs: $D2 locks the column but not the row. Every cell in a row checks column D of its own row, which is what lets one rule color the whole row.

Warn before things are late

Add these as extra rules on the same range, each with its own color:

HighlightCustom formulaColor
Due today=AND($D2=TODAY(), $B2<>"Done")Orange
Due in the next 3 days=AND($D2>TODAY(), $D2<=TODAY()+3, $B2<>"Done")Yellow

When several rules match the same cell, the one higher in the list wins. Keep the overdue rule at the top: drag it up in the Conditional formatting panel if needed.

Count what’s overdue

For a number at the top of the sheet: =COUNTIFS(D2:D200, "<"&TODAY(), B2:B200, "<>Done"). It counts tasks dated before today that aren’t done, and updates every day on its own.

If it doesn’t work

Overdue highlighting is one piece of a working tracker. See how it fits with status dropdowns in how to track projects in Google Sheets. In Lanez, late actions are flagged on their cards automatically, and the data still lives in your own Google Sheet.

Questions

Does TODAY() update by itself?

Yes. TODAY() recalculates whenever the sheet is opened or changed, so tomorrow’s overdue tasks turn red tomorrow without you touching anything.

Can I skip weekends?

For “due soon” warnings, swap TODAY()+3 for WORKDAY(TODAY(), 3). That counts three working days ahead, skipping Saturdays and Sundays.