How to track projects in Google Sheets

Updated October 9, 2026

A good project tracker in Google Sheets is one row per project, a handful of well-chosen columns, and formatting that makes problems jump out. It takes about 15 minutes to set up and stays readable even when you have dozens of projects.

The columns to use

Start with these and resist adding more until you miss something. Every extra column is one more thing to keep up to date.

ColumnWhat goes in itTip
ProjectA short nameMake it something people would say out loud
StatusPlanned, Active, Waiting, DoneA dropdown, so everyone uses the same words
OwnerOne personOne name, not a team: someone has to own it
Start dateWhen work beginsA real date, not text
Due dateWhen it should be finishedDrives the overdue flag below
Next stepThe very next actionThe most useful column in the sheet
NotesContext, blockers, linksKeep it short; link out to longer docs

Set it up step by step

  1. Name the tab “Projects” and add the headers in row 1. Freeze the row with View → Freeze → 1 row, so the headers stay put as you scroll.
  2. Turn Status into a dropdown. Select the Status cells below the header, then Insert → Dropdown, and give each status a color. The dropdown guide covers the options in detail.
  3. Make the date columns real dates. Select them, open Data → Data validation, and choose “Is valid date”. Now double-clicking a cell opens a date picker, and typos get flagged.
  4. Flag overdue projects. Use conditional formatting so a past due date turns red unless the project is done. The overdue dates guide has the exact formula.
  5. Add a summary tab. Create a second tab called “Summary” and count each status with =COUNTIF(Projects!B:B, "Active"), one line per status. Count overdue projects with =COUNTIFS(Projects!E:E, "<"&TODAY(), Projects!B:B, "<>Done").
  6. Give each person a view. Data → Filter views → Create new filter view, filter Owner to one name, and name the view after them. Each filter view has its own link to send, and using it doesn’t change what anyone else sees.

Keep it useful after week one

When a sheet stops being enough

A tracker answers “what’s the status of everything?” well. It’s weaker at “what’s moving and what’s stuck?”, which is what a Kanban board shows at a glance. The tracker vs Kanban guide explains the difference.

You don’t have to choose. Lanez reads a tracker laid out like this one and shows it as a drag-and-drop board, and every change is saved back to a Google Sheet in your Drive. Try it in the demo without signing up.

Questions

Does Google Sheets have a project tracker template?

Google’s template gallery (File → New → From template gallery) has a few project templates. They’re a fine start, but most mix several layouts in one tab. The layout above is simpler to keep up to date.

How many projects can one sheet handle?

Hundreds, as far as Sheets is concerned. What breaks first is readability: past about 30 active projects, lean on filter views and the summary tab instead of scrolling.

Should each project get its own tab?

No. One tab with one row per project is what lets you sort, filter and count. Put a project’s details in a linked doc, not in a separate tab.